Headquarters: NPKRR Maaligai, 144, Anna Salai, Chennai - 600 002

TANGEDCO (Tamil Nadu Generation and Distribution Corporation Limited) is the electricity utility responsible for the generation and distribution of power throughout the state of Tamil Nadu. The Citizen Charter outlines the service standards and commitments to consumers.

Objectives

  • Provide an overview of the organization and its functions
  • Establish clear service standards for electricity supply and connections
  • Define delivery timelines for various consumer services
  • Ensure transparency and accountability in service delivery
  • Enable consumers to understand their rights and the expected service levels

Service Standards — LT Connections

The following timelines apply for providing new Low Tension (LT) service connections:

ConditionTimeline
No extension work required30 days
Extension work required, no new transformer needed60 days
Extension work required, with new transformer installation90 days

Service Standards — HT & EHT Connections

The following timelines apply for providing new High Tension (HT) and Extra High Tension (EHT) service connections:

ConditionTimeline
HT — No extension work required60 days
HT — Extension work required, no new substation needed90 days
HT — Extension work required, with new substation180 days
EHT Connection270 days

Supply Interruption Restoration Standards

TANGEDCO commits to restoring electricity supply within the following timelines after an interruption:

CategoryTypeRestoration Timeline
Urban AreaHT Supply3 hours
Urban AreaLT Supply6 hours
Rural AreaHT Supply12 hours
Rural AreaLT Supply18 hours

Other Service Standards

ServiceTimeline
Name Transfer15 days (from receipt of all documents)
Tariff Change15 days
Meter Replacement (Faulty)7 days
Meter Testing (On Request)30 days
Billing Dispute Resolution60 days
Disconnection Notice Period15 days

Consumer Grievance Redressal

TANGEDCO has established a multi-tier grievance redressal mechanism:

  • Level 1: Area AE/O&M — First point of contact for all consumer complaints
  • Level 2: Executive Engineer — Escalation if unresolved within prescribed time
  • Level 3: Superintending Engineer — Further escalation
  • Level 4: CGRF (Consumer Grievance Redressal Forum) — Formal forum for unresolved grievances
  • Level 5: Electricity Ombudsman — Final appellate authority