TANGEDCO Logo

TANGEDCO

Tamil Nadu Generation and Distribution Corporation Limited

Thermal Power Stations

Overview

TANGEDCO operates coal-based thermal power stations with a combined installed capacity of approximately 4,060 MW. These stations are located across Tamil Nadu and form the primary baseload generation capacity for the state's electricity grid.

North Chennai Thermal Power Station (NCTPS)

Located at Athipattu in Thiruvallur district, North Chennai TPS is the largest thermal power station operated by TANGEDCO.

StageUnitsCapacity (MW)Status
Stage I3 × 210 MW630Operational
Stage II2 × 600 MW1,200Operational
Stage III1 × 800 MW800Operational
Total NCTPS2,630

Mettur Thermal Power Station (MTPS)

Situated near the Mettur Dam in Salem district, this station benefits from water availability from the Cauvery river system.

StageUnitsCapacity (MW)Status
Stage I4 × 210 MW840Operational
Stage III1 × 600 MW600Operational
Total MTPS1,440

Tuticorin Thermal Power Station (TTPS)

Located in Thoothukudi district on the southern coast of Tamil Nadu, the Tuticorin TPS uses imported coal and domestic coal blend.

StageUnitsCapacity (MW)Status
Stage I5 × 210 MW1,050Operational
Total TTPS1,050

Ennore Thermal Power Station (ETPS)

The Ennore Thermal Power Station, located in Chennai, was one of the earliest thermal power plants commissioned by TNEB. It had an original installed capacity of 450 MW. The station has been decommissioned after completing its operational life.

StationOriginal Capacity (MW)Status
Ennore TPS450Decommissioned

Total Thermal Capacity Summary

StationInstalled Capacity (MW)
North Chennai TPS2,630
Mettur TPS1,440
Tuticorin TPS1,050
Ennore TPS (Decommissioned)—
Total Operational Thermal~4,060 MW (approx.)

Related Pages